NEIGHBORHOOD 1b IMPROVEMENTS
NTP Date: 04/17/2025
SUbstantial Completion Date: 9/2026
Final completion date: 10/2026
Project Description
The project consists of full depth reconstruction of 22 street segments within the NBHD 1 B project area. This includes road reconstruction with subgrade stabilization, asphalt paving, concrete curb and gutter, and driveway replacements (limited to driveways that are within the existing right-of-way). The project aims to limit future construction disruptions by replacing aging water, sanitary sewer lines, select stormwater infrastructure, limited sidewalk improvements and street lighting.
The principal items of work are as follows:
- Full depth street reconstruction with subgrade stabilization.
- Asphalt Paving
- Concrete Curb and Gutter replacement along with replacement of driveways.
- Waterline Replacement including service connections.
- Sanitary Sewer Line Replacement including service connections.
- Storm Sewer infrastructure replacement where identified.
- Concrete sidewalk improvements.
Project Contacts
Jackie Barnes
Project Manager
972.561.8232
Jason Dyson
Project Superintendent
469.559.9441
Holly Horsak
Area Manager
602.350.5251
Where we're working
1. ROAD CLOSURE
Dates: 6/24/25 to 6/25/26
2. ROAD CLOSURE
Dates: 5/8 to TBD Pending ATMOS
3. ROAD CLOSURE
Dates: 9/25/25 to 5/30/26
4. ROAD CLOSURE
Dates: 1/09/26 to 5/30/26
5. ROAD CLOSURE
Dates: 4/27/25 to 8/21/26
6. ROAD CLOSURE
7. ROAD CLOSURE
Dates: 1/23/26 to 7/23/26
8. ROAD CLOSURE
Dates: 4/24 to 9/21/26
9. ROAD CLOSURE
Dates: 8/25/25 to 6/09/26
10. ROAD CLOSURE
Dates: 2/23/26 to 9/26/26
11. ROAD CLOSURE
Dates: 11/07/25 to 5/23/26
12. ROAD CLOSURE
Dates: 3/16/26 to 8/21/26
JOB PROGRESS













FUN FACT
From Courthouse to TWU and Beyond!
Sundt Construction is placing enough curb and gutter to stretch for over 31,462 linear feet? That’s more than the distance from the historic Denton County Courthouse-on-the-Square all the way to Texas Woman’s University and back with plenty to spare!
