NEIGHBORHOOD 2&6 IMPROVEMENTS
NTP Date: 12/2023
SUbstantial Completion Date: 10/2026
Project Description
Sundt is partnering with the City of Denton to complete package two of rehabilitation within the University of North Texas (UNT) and its surrounding neighborhoods. The scope of work includes a full in-depth street reconstruction that includes 85,764 SY of stabilized subgrade, 152,205 SY of asphalt pavement, 397TNs of lime slurry and the replacement of over 6,100 LF of sanitary sewer, 34 sanitary sewer manholes, 15,200 LF of concrete curb and gutter, 2,300 SY of driveways, and 1,800 SY of sidewalks.
The principal items of work are as follows:
- Full depth street reconstruction with subgrade stabilization.
- Asphalt Paving
- Concrete Curb and Gutter replacement along with replacement of driveways.
- Waterline Replacement including service connections.
- Sanitary Sewer Line Replacement including service connections.
- Storm Sewer infrastructure replacement where identified.
- Concrete sidewalk improvements.
Project Contacts
Ryan Cardinale Project Superintendent 469.953.0728
Holly Horsak
Area Manager
602.350.5251
Ryan Shockney
Project Manager
361.500.2413
Where we're working
1. ROAD CLOSURE
Location: Alice St.
Dates: 08/2025 to 06/2026
Closure Type: local traffic only
2. ROAD CLOSURE
Dates: 01/2026 to 04/2026
3. ROAD CLOSURE
Dates: 01/2026 to 04/2026
4. ROAD CLOSURE
Dates: 05/2025 to 04/2026
5. ROAD CLOSURE
Dates: 09/2025 to 04/2026
6. ROAD CLOSURE
Dates: 05/2025 to 07/2026
7. ROAD CLOSURE
Dates: 06/2025 to 05/2026
8. ROAD CLOSURE
Dates: 02/2026 to 07/2026
9. ROAD CLOSURE
Dates: 11/2025 to 04/2026
JOB PROGRESS


















FUN FACT
Fun fact: With the 192,000 square yards of asphalt, we are placing in package 3, you could pave a two-lane highway about 12 miles long. That’s enough to cover the distance from Denton, Texas, to the nearby city of Sanger, Texas, giving University of North Texas students a smooth ride to explore more of the Lone Star State!