Neighborhoods 2 & 6

NEIGHBORHOOD 2&6 IMPROVEMENTS

NTP Date: 12/2023
SUbstantial Completion Date: 10/2026

Project Description

Sundt is partnering with the City of Denton to complete package two of rehabilitation within the University of North Texas (UNT) and its surrounding neighborhoods.  The scope of work includes a full in-depth street reconstruction that includes 85,764 SY of stabilized subgrade, 152,205 SY of asphalt pavement, 397TNs of lime slurry and the replacement of over 6,100 LF of sanitary sewer, 34 sanitary sewer manholes, 15,200 LF of concrete curb and gutter, 2,300 SY of driveways, and 1,800 SY of sidewalks.

The principal items of work are as follows:
  • Full depth street reconstruction with subgrade stabilization.
  • Asphalt Paving
  • Concrete Curb and Gutter replacement along with replacement of driveways.
  • Waterline Replacement including service connections.
  • Sanitary Sewer Line Replacement including service connections.
  • Storm Sewer infrastructure replacement where identified.
  • Concrete sidewalk improvements.

Project Contacts

 Ryan Cardinale                                 Project Superintendent                          469.953.0728

Holly Horsak
Area Manager
602.350.5251

Ryan Shockney
Project Manager
361.500.2413

Where we're working

1. ROAD CLOSURE 

Location: Alice St.
Dates: 08/2025 to 06/2026
Closure Type: local traffic only

2. ROAD CLOSURE
 
Location: Sunset (East)
Dates: 01/2026 to 04/2026
Closure Type: local traffic only
3. ROAD CLOSURE
 
Location: Panhandle
Dates: 01/2026 to 04/2026
Closure Type: local traffic only
4. ROAD CLOSURE
 
Location: Ponder Ave.
Dates: 05/2025 to 04/2026
Closure Type: local traffic only
5. ROAD CLOSURE
 
Location: Emery and Fulton
Dates: 09/2025 to 04/2026
Closure Type: local traffic only
6. ROAD CLOSURE
 
Location: Scripture St. 
Dates: 05/2025 to 07/2026
Closure Type: local traffic only
7. ROAD CLOSURE
 
Location: Denton St.
Dates: 06/2025 to 05/2026
Closure Type: local traffic only
8. ROAD CLOSURE
 
Location: Bernard North
Dates: 02/2026 to 07/2026
Closure Type: local traffic only
9. ROAD CLOSURE
 
Location: Parkway
Dates: 11/2025 to 04/2026
Closure Type: local traffic only
 
 
 
 
 

JOB PROGRESS

FUN FACT

  • Fun fact: With the 192,000 square yards of asphalt, we are placing in package 3, you could pave a two-lane highway about 12 miles long. That’s enough to cover the distance from Denton, Texas, to the nearby city of Sanger, Texas, giving University of North Texas students a smooth ride to explore more of the Lone Star State!