Neighborhoods 2 & 6

NEIGHBORHOODS 2 & 6 ROADWAY IMPROVEMENTS

NTP Date: 12/15/2023

Substantial Completion Date: 09/16/2026

Project Description

Sundt is partnering with the City of Denton to complete package two of rehabilitation within the University of North Texas (UNT) and its surrounding neighborhoods.  The scope of work includes a full in-depth street reconstruction that includes 85,764 SY of stabilized subgrade, 152,205 SY of asphalt pavement, 397TNs of lime slurry and the replacement of over 6,100 LF of sanitary sewer, 34 sanitary sewer manholes, 15,200 LF of concrete curb and gutter, 2,300 SY of driveways, and 1,800 SY of sidewalks.

Project Contacts

Ryan Cardinale
Project Superintendent
469.953.0728

Holly Horsak
Project Manager
602.350.5251

Ryan Shockney
Project Engineer
361.500.2413

Where we’re working

 

 
Road Open to Residential Traffic Only

    • Location: Bernard St. South
        • Dates: 03/9/2024 -6/30/2025

    • Location: Welch St.
        • Eagle to Highland Dates: 03/21/2024 – 06/11/2025

        • Highland to Prairie Dates: 4/30/25 – 8/01/25

        • Sycamore to Mulberry Dates: 4/8/25 – 10/14/25

    • Location: Aileen St.
        • Dates: 10/28/2024 – 07/18/2025

    • Location: Margie St.
        • Dates: 2/24/2024 – 05/25/2025

    • Location: Mulberry St.
        • Dates: 04/08/2025 – 07/03/2025

    • Location: Fannin St.
        • Dates: 12/09/2024 – 06/04/2025

    • Location: Avenue B
        • Dates: 5/04/2025 – 06/04/2025

    • Location: Sunset St
        • Dates: 01/06/2025 – 03/19/2025

    • Location: Mounts St.
        • Dates: 05/25/2025 – 08/04/2025

    • Location: Avenue G
        • Dates: 03/07/2025 – 06/18/2025

    • Location: Avenue A
        • Dates: 05/06/25 – 06/09/2025

    • Location: Congress St. West
        • Dates: 02/18/2025 – 06/05/2025

    • Location: Crescent St. East
        • Dates: 03/31/2025 – 06/06/2025


VISIT THE CITY OF DENTON’S IMPROVEMENTS Page

JOB PROGRESS

Asphalt removal on Maple St. North

 

Asphalt removal on Maple St. North

Sidewalk, curb & gutter removal on Maple St. North

 

Sidewalk, curb & gutter removal on Maple St. North

Excavation preparation on Maple St. North

 

Excavation preparation on Maple St. North

Addition of hydrated lime on Maple St. North

 

Addition of hydrated lime on Maple St. North

First layer of asphalt on Maple St. North

 

First layer of asphalt on Maple St. North

Trenching on Crescent St. for sewer lines.

 

Trenching on Crescent St. for sewer lines.

Curb and gutter pour on north half of Maple St.

 

Curb and gutter pour on north half of Maple St.

Curb and Gutter pour on Broadway St.

 

Curb and Gutter pour on Broadway St.

Maple St. North 2nd lift of Asphalt

 

Maple St. North 2nd lift of Asphalt

Asphalt Paving for 1st Lift on Maple St. South

 

Asphalt Paving for 1st Lift on Maple St. South

Lime Slurry Mixing for Crescent St.

 

Lime Slurry Mixing for Crescent St.

Curb & Gutter on Hillcrest

 

Curb & Gutter on Hillcrest

Hillcrest St. Overview

 

Hillcrest St. Overview

Hillcrest St. Driveway

 

Hillcrest St. Driveway

Sundt Craft during Concrete Placement

 

Sundt Craft during Concrete Placement

Sundt Craft during Concrete Placement

 

Sundt Craft during Concrete Placement

Sundt Craft during Concrete Placement

 

Sundt Craft during Concrete Placement

Sundt Craft during Concrete Placement

 

Sundt Craft during Concrete Placement

Sundt Craft during Concrete Placement

 

Sundt Craft during Concrete Placement

Sundt Craft during Concrete Placement

 

Sundt Craft during Concrete Placement

Sundt Craft Finishing Concrete

 

Sundt Craft Finishing Concrete

Sundt Craft Finishing Concrete

 

Sundt Craft Finishing Concrete

Sundt Craft Finishing Concrete

 

Sundt Craft Finishing Concrete

Sundt Craft Grading Subgrade

 

Sundt Craft Grading Subgrade

Sundt Craft Grading Subgrade

 

Sundt Craft Grading Subgrade

Sundt Craft Grading Subgrade

 

Sundt Craft Grading Subgrade

Sundt Craft Grading Subgrade

 

Sundt Craft Grading Subgrade

Sundt Craft Grading Subgrade

 

Sundt Craft Grading Subgrade

Sundt Craft Grading Subgrade

 

Sundt Craft Grading Subgrade

Sundt Craft Grading Subgrade

 

Sundt Craft Grading Subgrade

FUN FACT

In package 1, Sundt will place enough curb and gutter to circle the football field over 11 TIMES!