NEIGHBORHOOD 1b IMPROVEMENTS
NTP Date: 04/17/2025
SUbstantial Completion Date: TBD
Project Description
The project consists of full depth reconstruction of 22 street segments within the NBHD 1 B project area. This includes road reconstruction with subgrade stabilization, asphalt paving, concrete curb and gutter, and driveway replacements (limited to driveways that are within the existing right-of-way). The project aims to limit future construction disruptions by replacing aging water, sanitary sewer lines, select stormwater infrastructure, limited sidewalk improvements and street lighting.
The principal items of work are as follows:
- Full depth street reconstruction with subgrade stabilization.
- Asphalt Paving
- Concrete Curb and Gutter replacement along with replacement of driveways.
- Waterline Replacement including service connections.
- Sanitary Sewer Line Replacement including service connections.
- Storm Sewer infrastructure replacement where identified.
- Concrete sidewalk improvements.

Project Contacts
Ryan Cardinale
Project Superintendent
469.953.0728
Holly Horsak
Area Manager
602.350.5251
Jeremiah Beiter
Sr. Project Manager
469.724.6338
Where we're working

1. ROAD CLOSURE
Location: TBD
Dates: TBD
Closure Type: TBD
JOB PROGRESS






























FUN FACT
In package 1, Sundt will place enough curb and gutter to circle the football field over 11 TIMES!